Company Description:

"Caldwell Marine International, LLC is a marine construction contractor specializing in submarine utility operations. CMI's main focus is marine construction, submarine power cables, fiber optic submarine cables and systems worldwide.

In operation for over 65 years, CMI has successfully carried out the installation and repair of hundreds of submarine power and telecommunications cables worldwide. CMI has successfully built and rehabilitated many piers and docks, as well as installed many unique marine structures that require advanced installation techniques. With a wide range of specialized marine construction equipment, an Atlantic waterfront yard, and over 150 years of marine construction experience on staff, Caldwell is ready to take on any marine construction project."

Services Offered:

Marine Construction Company Atlantic Marine Construction Submarine Cable Construction
Pacific Marine Construction Marine Construction Services Submarine Power Cable Installation

Web Results:

Installed transmission...
Caldwell Marine International, LLC successfully installed two 180 foot steel transmission towers supporting new 230kV transmission lines spanning the Mullica River. Heavy marine construction operations included the construction of dry river cofferdams, bulkheads, driving of over 160 pipe piles, and ...
Water treatment plant...
Construction of a new membrane treatment facility, new high lift pumping facilities totaling 36 MDG, upgrades of the gravity filter control system and associated improvements to the plant infrastructure. The capacity of the state of the art membrane treatment facility is 12 MGD, expandable to 24 MGD...
Saw Mill Valley Trunk...
Contract No. 03-517 Saw Mill Valley Trunk Sewer Repair. Clean 924 LF of existing 60 and 66 concrete pipe and rehabilitate using the slipline process with 54 and 60 Hobas brand fiberglass pipe under active flow conditions. The annular space was filled with cellular grout. Three insertion pits were re...
Restoration of Upper...
Contract No. 2006-1 Work included the demolition of existing earthen dams and timber spillways and the complete reconstruction using roller compacted concrete (RCC) and precast post-tensioned spillways. A total of 14,700 CY of (RCC) was placed in 14 lifts atop approximately 2000 CY of conventional m...
Installed 72 concrete...
Modern Microtunneling Project Description Installation of 900LF of 72 concrete pipe across the Hackensack River, Little Ferry, NJ Excavation depths ranged from 20 to 45 Pipe lengths of 20 were placed on pile supported concrete caps. Sequence of Operation Temporary earthen terms were constructed at e...

Business Information:

In Business Since:1987